GB 50500-2013 第9.10.1条
| **** | **Site visa adjustment**: Where the contractor is required by the employer to complete sporadic work outside the contract, or work arising from events not attributable to the contractor, the employer shall promptly issue a written instruction to the contractor and provide the relevant information required. The contractor shall, within 7 days of receiving the instruction, submit a site visa report to the employer. |