GB 50500-2013 第9.2.1条 Code of Bills of Quantities and Valuation for Construction Works

Contract price adjustment成本造价

GB 50500-2013 第9.2.1条

| **** | **Quantity deviation adjustment**: When the quantity deviation exceeds 15%, the comprehensive unit price for the excess portion shall be adjusted. When the quantity increases by more than 15%, the comprehensive unit price for the excess portion shall be lowered; when the quantity decreases by more than 15%, the comprehensive unit price for the remaining portion after the decrease shall be raised. |