GB 50500-2013 第7.3.1条
| **** | **Schedule delay and contract price**: If the schedule is delayed due to the employer's reasons, the price of the works after the planned progress date shall adopt **the higher of the planned progress date and the actual progress date**; if the schedule is delayed due to the contractor's reasons, **the lower** shall be adopted. |