GB 50500-2013 第7.3.1条 Code of Bills of Quantities and Valuation for Construction Works

Contract Price Agreement成本造价

GB 50500-2013 第7.3.1条

| **** | **Schedule delay and contract price**: If the schedule is delayed due to the employer's reasons, the price of the works after the planned progress date shall adopt **the higher of the planned progress date and the actual progress date**; if the schedule is delayed due to the contractor's reasons, **the lower** shall be adopted. |