GB 50500-2013 第6.3.2条
| **** | **Pricing strategy**: Bidders are permitted to use unbalanced bidding, provided it is reasonable. For example:<br>• Unit prices may be appropriately increased for early-stage works such as earthworks and foundation engineering (to recover funds as early as possible);<br>• Unit prices may be appropriately reduced for later-stage works such as hotel fine decoration and extra-low voltage (ELV) works (to improve competitiveness for award);<br>• Higher prices may be quoted for bill items whose quantities are likely to increase (e.g., guest room sockets, light fixtures), and lower prices for items likely to decrease (e.g., temporary facilities). |