GB 50500-2013 第4.1.5条 Code of Bills of Quantities and Valuation for Construction Works

Preparation of bill of quantities成本造价

GB 50500-2013 第4.1.5条

| **** | **The safety and civilized construction fee in the list of measure items must be priced in accordance with the regulations of the national, provincial, or industry construction authorities and shall not be treated as a competitive fee.** During hotel construction, personnel turnover is high, so the safety and civilized construction fee is usually listed separately at **2.0%~3.5%** of the divisional and sub-divisional works cost (subject to local standards). |

Other clauses of this standard

Still have a specific question? Ask a MEP expert

12 hotel MEP experts online, answers cite standard clauses you can verify.

Ask free →

Engineering reference only — verify against project conditions and the latest codes.