GB 50500-2013 第11.5.1条 Code of Bills of Quantities and Valuation for Construction Works

Completion settlement成本造价

GB 50500-2013 第11.5.1条

| **Summary of Completion Settlement Price**: The calculation formula is: Total Completion Settlement Price = Divisional and Sub-divisional Works Cost + Measure Project Cost + Other Project Cost + Statutory Fees + Taxes. For hotel projects, note that the "engineering pollutant discharge fee" within the statutory fees shall be calculated based on actual payment vouchers.