GB 50300-2013 第6.0.5条 Unified Standard for Constructional Quality Acceptance of Building Engineering

Acceptance procedures and organization机电综合

GB 50300-2013 第6.0.5条

| | When a unit project is constructed by a subcontractor, the subcontractor shall inspect and assess the contracted works in accordance with the procedures specified in this standard, and the general contractor shall send personnel to participate. Upon completion of the subcontracted works, the relevant project documents shall be handed over to the general contractor. The MEP and fit-out subcontracting works commonly found in hotel buildings must strictly comply with this clause. |

Other clauses of this standard

Still have a specific question? Ask a MEP expert

12 hotel MEP experts online, answers cite standard clauses you can verify.

Ask free →

Engineering reference only — verify against project conditions and the latest codes.