GB 50300-2013 第1.0.9条
| | The construction project quality acceptance procedure and organization shall comply with the following provisions:<br>1. Inspection lots and sub-item works shall be accepted under the organization of the supervision engineer (or the project technical director of the construction unit), together with the project professional quality (technical) director of the contractor and relevant personnel.<br>2. Division works shall be accepted under the organization of the chief supervision engineer (or the project director of the construction unit), together with the project director and the technical and quality directors of the contractor; the project directors of the survey and design units for the foundation and main structure division works shall also participate in the acceptance of the relevant division works.<br>3. After completion of a unit work, the contractor shall organize relevant personnel to carry out inspection and assessment on its own and submit a project acceptance report to the construction unit.<br>4. Upon receipt of the project acceptance report, the construction unit shall organize the project directors of the contractor (including subcontractors), design unit, supervision unit and other units to conduct acceptance of the unit (sub-unit) work.<br>5. Where a unit work is constructed by subcontractors, the subcontractors shall inspect and assess the contracted works in accordance with the procedure specified in this standard, and the general contractor shall assign personnel to participate. Upon completion of the subcontracted works, the relevant documents shall be handed over to the general contractor.<br>6. Where the parties participating in acceptance disagree on the project quality acceptance, the matter may be referred to the local construction administrative department or project quality supervision agency for coordination and resolution.<br>7. After the unit work passes quality acceptance, the construction unit shall, within the specified time, submit the project completion acceptance report and relevant documents to the construction administrative department for record.