GB 50300-2013 第6.0.3条 Unified Standard for Constructional Quality Acceptance of Building Engineering

Acceptance Procedures and Organization机电综合

GB 50300-2013 第6.0.3条

| | After completion of a unit project, the contractor shall organize relevant personnel to conduct inspection and assessment, and submit a project completion report to the client. The project completion report shall be reviewed and signed by the project manager and the relevant responsible person of the contractor. |