| **** | The alarm valve assembly shall undergo the following functional checks:<br>1. Inspect once a month and conduct a drain test to check the operation of the alarm bell, hydraulic alarm bell, and pressure switch;<br>2. Each quarter, conduct a water supply test on the drain test valve next to the alarm valve to verify the system's water supply capacity. |