GB 50261-2017 第5.8.5条 Code for construction and acceptance of sprinkler systems

Construction消防工程

GB 50261-2017 第5.8.5条

| **** | During commissioning of the wet alarm valve assembly, water is discharged from the test connection; when the inlet pressure of the wet alarm valve is greater than 0.14 MPa and the discharge flow rate is greater than 1 L/s, the alarm valve shall start promptly; the water motor alarm with a retard chamber shall sound the alarm bell within 5–90 s. |

Other clauses of this standard

Still have a specific question? Ask a MEP expert

12 hotel MEP experts online, answers cite standard clauses you can verify.

Ask free →

Engineering reference only — verify against project conditions and the latest codes.