GB 50261-2017 第5.8.1条 Code for construction and acceptance of sprinkler systems

Construction消防工程

GB 50261-2017 第5.8.1条

| **** | System commissioning shall be carried out after system construction is completed. Commissioning shall include water source testing, fire water supply commissioning, jockey pump commissioning, alarm valve group commissioning, drainage facility commissioning, and linkage tests. |