GB 50261-2017 第5.7.1条 Code for construction and acceptance of sprinkler systems

Construction消防工程

GB 50261-2017 第5.7.1条

| **** | Pipe network flushing shall be carried out section by section after the pressure test has passed. The flushing sequence shall be outdoor first, then indoor; underground first, then aboveground; the flushing of indoor sections shall proceed in the order of water distribution main pipes, water distribution pipes, and water distribution branch pipes. |