GB 50261-2017 第5.6.4条 Code for construction and acceptance of sprinkler systems

Construction消防工程

GB 50261-2017 第5.6.4条

| **** | The water pressure tightness test shall be conducted after the water pressure strength test and pipe network flushing have passed. The test pressure shall be the design working pressure, held for 24 h, with no leakage. |

Other clauses of this standard

Still have a specific question? Ask a MEP expert

12 hotel MEP experts online, answers cite standard clauses you can verify.

Ask free →

Engineering reference only — verify against project conditions and the latest codes.