| **** | The fire pump adapter shall be installed in the following order: inlet, body, connecting pipe, check valve, safety valve, drain pipe, and control valve. The check valve shall be installed in the direction that allows fire water to enter the system from the fire pump adapter (clear signage is required outdoors at the hotel). |