What should be prepared before drawing design begins?

Expert Q&APaul Qiao · MEP DirectorUpdated 2026-06-24
P
Paul Qiao
MEP Director

What should be prepared before drawing design begins?

This question is very much to the point and directly addresses the core work of the MEP Director at the project initiation stage. Drawing design is not about drawing as soon as you start; it is about "troops and horses not yet moving, but provisions and fodder going first." As the MEP Director, before drawing design begins, I must ensure that preparations across the following six dimensions are fully in place; otherwise, subsequent design will inevitably require rework, clash, and exceed the budget.

---

1. Confirmation of Brand Standards and Design Brief

This is the "constitution" of all design.

---

2. Full-Discipline Interface Division and MEP Point Load Information List

This is the insurance against "drawing clashes."

---

3. Investigation of Municipal Conditions and Local Policies and Regulations

This is the key to determining whether the system scheme can be implemented.

---

4. Full-Discipline Pipeline Coordination Principles and Clear Height Control Strategy

This is the MEP Director's most core coordination work.

---

5. Fire Protection System Scheme and Submission Review Prejudgment

This is a red line—there is no room for any wishful thinking.

---

6. Cost Budget and Bidding Strategy

This is what the owner cares about most.

---

Summary: MEP Director's "Pre-design Checklist"

| No. | Preparation Item | Key Action | Standard/Code Reference | Decision Point |
|------|--------|----------|----------------|--------|
| 1 | Brand standard confirmation | Obtain the latest MEP standards, hold a standard alignment meeting | Brand MEP Design Criteria | Issue"Technical Deviation Application"when brand and local codes conflict |
| 2 | All-discipline data submission | Develop"Point Location Data Submission Schedule", review interior finish point location drawings | GB/T 50328 | Decide whether to adopt BIM when pipeline conflicts occur |
| 3 | Municipal conditions survey | Obtain power supply, water supply, gas, and drainage approvals | GB 50052/50015/50028 | Initiate alternative scheme assessment when municipal utilities are unavailable |
| 4 | Pipeline coordination principles | Develop"Pipeline Coordination Design Guidelines", clarify clear height control | GB 50222 | Pipeline treatment scheme for areas without suspended ceilings |
| 5 | Fire protection scheme pre-review | Hold fire protection pre-review meeting, clarify system forms | GB 50016/50116 | Decision on controversial items such as fire hose reels |
| 6 | Cost budget lock-in | Complete equipment selection list, issue quota design indicators | GB 50500 | Assessment of impact of downgrade schemes on operations |

Final word of advice: Before drawing design begins, the MEP Director must hold at least 3 "all-discipline coordination meetings" (architecture, structure, interior finish, landscape, MEP) and produce"Design Kick-off Meeting Minutes"signed and confirmed by all parties. If any party has not signed, drawing design must never start. This is experience earned through blood and tears.

Standard reference

GB 50736GB/T 50328GB 50052GB 50015GB 50016GB 50014

More from this expert

Still have a specific question? Ask a MEP expert

12 hotel MEP experts online, answers cite standard clauses you can verify.

Ask free →

Engineering reference only — verify against project conditions and the latest codes.