The incoming cable specification for a 25000KVA transformer — answer only the cable specification.

Expert Q&APaul Qiao · MEP DirectorUpdated 2026-07-13
P
Paul Qiao
MEP Director

The incoming cable specification for a 25000KVA transformer — answer only the cable specification.

Based on the 25000 kVA transformer capacity you provided, combined with Article 3.0.1 of GB 50052-2009 "Code for Design of Power Supply and Distribution Systems" (the supply voltage shall be determined according to the power consumption capacity) and the ampacity selection principles of GB 50217-2018 "Standard for Design of Cables of Electric Engineering," this capacity has far exceeded the economically applicable range of 10 kV supply. Typically, a supply voltage of 35 kV or higher is required. The cable specifications corresponding to two common schemes are provided below:

Scheme 1: 35 kV Supply (Recommended Scheme)

Scheme 2: 10 kV Supply (Feasibility to Be Confirmed, Usually Not Economical)
Key Notes:
1. Voltage Level Priority: For a 25000 kVA transformer, a 35 kV incoming line should be the first choice; the 10 kV scheme requires approval by the local power supply department (usually the upper limit of single-circuit 10 kV supply capacity is approximately 10000–12000 kVA, Article 3.2.2 of GB 50053-2013).
2. Number of Cables and Laying Method: The final specification shall be comprehensively calculated in combination with the cable laying method (cable tray, conduit bank, direct burial), ambient temperature, and correction factors for multiple cables in parallel (Articles 3.7.3–3.7.5 of GB 50217-2018). It is recommended to commission a professional design institute to issue a cable cross-section calculation report.
3. Protection and Grounding: 35 kV cables shall be provided with grounding conductors (cross-section ≥25mm² copper core) and shall meet the grounding requirements for metallic shields in Article 3.8.1 of GB 50217-2018.

Please refer to the formal construction drawings of the design institute; the above are recommended specifications based on the codes.

Standard reference

GB 50052-2009GB 50217-2018GB 50053-2013GB 50217-2018.

More from this expert

Still have a specific question? Ask a MEP expert

12 hotel MEP experts online, answers cite standard clauses you can verify.

Ask free →

Engineering reference only — verify against project conditions and the latest codes.