GB 50054-2011 第7.3.4条 Code for Design of Low-Voltage Power Distribution

Laying of power distribution lines电气工程

GB 50054-2011 第7.3.4条

| | When wires are installed in conduits, the total cross-sectional area of the wires inside the conduit (including insulation) shall not exceed 40% of the internal cross-sectional area of the conduit. For conduit runs in hotel guest rooms, the bending radius shall not be less than 6 times the outer diameter of the conduit. |