GB 50015-2019 第4.2.3条 Standard for Design of Building Water Supply and Drainage

Water feature给排水

GB 50015-2019 第4.2.3条

| Pumps for water feature projects should be submersible pumps; when dry installation is used, drainage facilities should be provided. The flow rate and head of the pumps should be determined according to the water feature design requirements, and standby pumps should be provided (when the water feature is large in scale or high operational reliability is required).