GB 51309-2018 第6.0.1条
| **** | After the system is completed, the construction unit shall organize the construction, design, supervision and other units to conduct acceptance. If acceptance fails, the system shall not be put into use. |
| **** | After the system is completed, the construction unit shall organize the construction, design, supervision and other units to conduct acceptance. If acceptance fails, the system shall not be put into use. |