GB 50242-2002 第11.4.1条 Code for Acceptance of Construction Quality of Building Water Supply, Drainage and Heating Engineering

System commissioning给排水

GB 50242-2002 第11.4.1条

| **** | After the hot water supply system is installed, a hydrostatic test shall be carried out before the pipeline insulation is applied. The test pressure shall comply with the design requirements. |