GB 50242-2002 第6.2.8条 Code for Acceptance of Construction Quality of Building Water Supply, Drainage and Heating Engineering

Indoor hot water给排水

GB 50242-2002 第6.2.8条

| **** | **After the hot water supply system is installed, system commissioning shall be carried out.** The commissioning content includes: the flow rate and head of the hot water circulation pump; the hot water supply temperature; the return water temperature; the supply water temperature at the most unfavorable point of the system, etc., and shall meet the design requirements. |