GB 50974-2014 第13.1.4条 Technical code for fire protection water supply and hydrant systems

Commissioning消防工程

GB 50974-2014 第13.1.4条

| **** | Fire pump commissioning: when started automatically or manually, it should be put into normal operation within 55s; when the standby power supply is switched, the pump should complete startup within 1min. |