GB 50974-2014 第12.3.11条 Technical code for fire protection water supply and hydrant systems

Construction消防工程

GB 50974-2014 第12.3.11条

| **** | Construction records, concealed works acceptance records, and pressure test reports for the fire water supply system shall be complete and accurate. As a high-occupancy venue, all concealed works during construction of the hotel (such as buried pipes and pipes above ceilings) must pass acceptance by the supervisor or the construction unit before being concealed. |