GB 51251-2017 第9.4.2条 Technical Standard for Smoke Control and Exhaust Systems in Buildings

Construction and Commissioning消防工程

GB 51251-2017 第9.4.2条

| **** | During integrated commissioning, fire signals should be simulated to test the actuation logic of the smoke control system (stairwell and vestibule supply air outlets and fan interlock) and the smoke exhaust system (smoke exhaust outlets, smoke exhaust valves, smoke exhaust fans, and make-up air fans interlock). For hotels, particular emphasis should be placed on testing the interlock relationship between corridor smoke exhaust and stairwell pressurization air supply. |

Other clauses of this standard

Still have a specific question? Ask a MEP expert

12 hotel MEP experts online, answers cite standard clauses you can verify.