GB 50243-2016 第11.3.1条 Code for Acceptance of Construction Quality of Ventilation and Air Conditioning Works

System commissioning暖通空调

GB 50243-2016 第11.3.1条

| **** | The system air volume commissioning result shall not deviate from the design air volume by more than 10%. For high-ceiling spaces such as the hotel lobby and banquet hall, uniform air supply must be ensured, and the fresh air volume in guest rooms must meet hygiene standards. |