GB 50243-2016 第11.2.2条 Code for Acceptance of Construction Quality of Ventilation and Air Conditioning Works

System commissioning暖通空调

GB 50243-2016 第11.2.2条

| **** | For major equipment such as fans, pumps, and chillers, the single-machine trial run shall be continuous for no less than 2 hours, and the bearing temperature rise, vibration, and noise shall meet the requirements of the equipment technical documents. For equipment in hotel guest room areas, vibration and noise control shall be prioritized. |