GB 50243-2016 第8.6.1条 Code for Acceptance of Construction Quality of Ventilation and Air Conditioning Works

Air-conditioning cooling system暖通空调

GB 50243-2016 第8.6.1条

| **** | After the refrigeration system is installed, system blow-down (purge with dry compressed air or nitrogen at 0.5~0.6MPa until no debris is discharged) and tightness testing (e.g., leak detection with a halogen leak detector or soap solution) must be carried out. |