GB 50243-2016 第6.3.7条 Code for Acceptance of Construction Quality of Ventilation and Air Conditioning Works

Ductwork system installation暖通空调

GB 50243-2016 第6.3.7条

| **** | After the duct system is installed, duct air leakage testing shall be carried out (20% sampling for medium-pressure systems, 5% sampling for low-pressure systems). **(Hotel fresh air and exhaust systems are mostly medium/low pressure; this clause ensures system energy efficiency and hygiene requirements)** |