GB 50243-2016 第6.3.6条 Code for acceptance of construction quality of ventilation and air conditioning works

Ductwork system installation暖通空调

GB 50243-2016 第6.3.6条

| **** | After the duct system is installed, tightness testing shall be carried out according to the system category. **(Different systems such as hotel guest room areas, public areas, and kitchen areas shall be tested separately to ensure that the air leakage rate meets the standard)** |