GB 50243-2016 第3.0.7条 Code for Acceptance of Construction Quality of Ventilation and Air Conditioning Works

Basic Requirements暖通空调

GB 50243-2016 第3.0.7条

| | Finished product protection should be carried out properly during construction. In hotel construction, installed air-conditioning equipment, air outlets, valves, etc. must be protected from contamination or damage during subsequent fit-out works. |