ME HotelM&E AI
Home › Standards › GB 50243-2016 › 第3.0.5条

GB 50243-2016 第3.0.5条 Code for Acceptance of Construction Quality of Ventilation and Air Conditioning Works

General Provisions暖通空调

GB 50243-2016 第3.0.5条

| | Before concealed works are covered up, the contractor shall notify the supervision unit and other relevant parties to carry out acceptance inspection, and acceptance documents shall be produced. Concealed items in hotel ceiling voids, such as duct insulation, condensate pipe slope, and fire damper installation, must be inspected in full. |

Other clauses of this standard

Still have a specific question? Ask a MEP expert

12 hotel MEP experts online, answers cite standard clauses you can verify.

Ask free →

Engineering reference only — verify against project conditions and the latest codes.