Design of Liability for Breach and Claim Clauses in Hotel MEP Procurement Contracts

Procurement and TenderingUpdated 2026-05-13

I am procurement expert (Martin Chen), well versed in standards such as GB/T 31384. In hotel MEP procurement, breach of contract liability and claim clauses are the core line of d…

Design of Liability for Breach and Claim Clauses in Hotel MEP Procurement Contracts

I am procurement expert (Martin Chen), well versed in standards such as GB/T 31384. In hotel MEP procurement, breach of contract liability and claim clauses are the core line of defense in contract management and are directly related to project schedule, cost control and risk avoidance. Based on my years of experience in high-end hotel projects (such as Marriott and Hilton series), if these clauses are improperly designed, the owner may be placed in a passive position when the supplier fails to perform, and legal disputes may even arise. Therefore, clause design must be based on GB/T 31384 "Hotel Management Specifications" and the Contract Part of the "Civil Code", and combined with the characteristics of MEP equipment to ensure operability and fairness.

First, breach of contract liability clauses should clearly cover three aspects: **delivery delay, quality defects and performance failure**. According to Article 6.3.2 of GB/T 31384, the supplier must deliver at the time agreed in the contract, and delay shall be subject to liquidated damages calculated on a daily basis (usually 0.1%-0.5% of the total contract price, with the cumulative amount not exceeding 10%). For example, in the procurement of air handling units for a five-star hotel, the supplier delayed delivery by 30 days. We claimed 0.3% per day and ultimately obtained 9% in liquidated damages, covering the cost of temporarily leased equipment. Quality defect clauses need to reference Article 7.2.1 of GB/T 31384, requiring the supplier to be responsible for failures during the equipment warranty period (usually 2 years), and liquidated damages may be set at 1.5 times the repair cost. For performance failure (such as cooling capacity lower than the contracted value by more than 5%), the owner should be allowed to return the goods or handle it through a price reduction, with liquidated damages of 5%-15% of the contract price.

Second, claim clauses should be designed with clear **trigger conditions, calculation methods and time limits**. Trigger conditions include: the supplier fails the arrival acceptance inspection (such as appearance damage or specification mismatch), commissioning failure, or operating data failing to meet standards. The calculation method must be based on actual losses, such as hotel business interruption losses caused by equipment failure (calculated according to average daily revenue). Regarding time limits, according to Article 621 of the "Civil Code", the owner should notify in writing within 30 days after discovering the breach; otherwise, the right to claim may be lost. For example, in the procurement of distribution cabinets for a hotel, the brand of circuit breakers provided by the supplier did not match. We claimed the equipment price difference and installation rework costs based on the contract clauses, totaling RMB 120,000.

Practical case: An international brand hotel procured chillers, and the contract set performance test clauses: when the COP value is 0.2 lower than the promised value, a claim of 2% of the contract price shall be made for each 0.1. Testing found that the actual COP was 0.3 lower. We claimed 6%, and the supplier ultimately compensated RMB 180,000 and replaced the compressor free of charge. This avoided later operational energy consumption losses.

Summary: Breach of contract liability and claim clauses need to be specific, quantified, and supported by references to standards (such as GB/T 31384) and actual loss data in order to effectively protect the owner's rights and interests. The above are reference opinions. The actual project situation still needs to be further comprehensively evaluated and implemented in combination with specific operating conditions, site conditions and other factors.

Still have a specific question? Ask a MEP expert

12 hotel MEP experts online, answers cite standard clauses you can verify.

Ask free →

Engineering reference only — verify against project conditions and the latest codes.