What should be noted during equipment arrival acceptance inspection?

Procurement and TenderingUpdated 2026-04-27

Check the brand, model and serial number; inspect the appearance (for rust/dents); and verify that the certificate of conformity, test report and manual are complete. Fire protect…

What should be noted during equipment arrival acceptance inspection?

Check the brand, model and serial number; inspect the appearance (for rust/dents); and verify that the certificate of conformity, test report and manual are complete. Fire protection products must have fire product certification. For imported equipment, check the customs declaration form.