Which MEP general contracting contract model is better for hotels?

Cost estimationUpdated 2026-04-27

A fixed lump sum contract suits projects with complete bills of quantities and drawings and a clear construction schedule; a rate based contract suits projects with incomplete dra…

Which MEP general contracting contract model is better for hotels?

A fixed lump-sum contract suits projects with complete bills of quantities and drawings and a clear construction schedule; a rate-based contract suits projects with incomplete drawings and frequent variations. It is recommended to use a lump-sum approach for the main scope, with a provisional sum reserved for disputed items, to avoid low-price winning bids followed by high-price settlements.