[MEP Director] How long is the design cycle for a hotel MEP system typically?

MEP DirectorUpdated 2026-04-27

Depending on scale and complexity, schematic design generally takes 3 5 days, preliminary design 7 14 days, and construction drawing design 14 30 days. For five star hotels, due t…

[MEP Director] How long is the design cycle for a hotel MEP system typically?

Depending on scale and complexity, schematic design generally takes 3-5 days, preliminary design 7-14 days, and construction drawing design 14-30 days. For five-star hotels, due to system complexity, it is recommended to allow sufficient design time to avoid later changes.