Analysis of Key Technical Points in Weak Current Intelligent Construction

Weak-current intelligent systems Updated 2026-04-25 0 views

Systematically summarize the key technical points and quality control measures during the construction of ELV (extra low voltage) intelligent systems, covering the process requirements of core construction sta…

1. Key points for conduit laying and embedded construction

Low-voltage conduit laying is a key part of concealed works and must strictly follow GB 50303-2015 and GB 50312-2016. Main technical requirements: metal conduits shall use hot-dip galvanized steel pipes Φ20-Φ50, with wall thickness ≥1.5 mm for exposed installation or ≥2.0 mm for concealed installation; conduit bending radius shall be no less than 6 times the pipe diameter for concealed installation or 4 times for exposed installation; pipe clamp fixing spacing shall be no more than 1.5 m, with one fixing point at each end of a bend; the spacing between power and low-voltage conduits shall be ≥300 mm for parallel laying and ≥100 mm for crossing.

2. Equipment installation and termination process requirements

Low-voltage equipment installation must meet the requirements of equipment technical manuals and design drawings. Core points: cabinet base height ≥300 mm; cabinet verticality deviation ≤1.5 mm/m and horizontality deviation ≤2 mm/m; patch panel termination shall adopt the T568B standard, with untwisted pair length ≤13 mm, and cable labels after termination shall be clear and durable; camera installation height 2.5-5 m indoors or 3.5-10 m outdoors, with no obstruction in the viewing area, and IP protection rating ≥IP66 outdoors.

3. System grounding and equipotential bonding

Low-voltage system grounding is key to ensuring stable system operation and lightning protection. Technical requirements are based on GB 50174-2017 and GB 50057-2010: the low-voltage system shall adopt a common grounding method with grounding resistance ≤1 ohm; the low-voltage equipment room shall be provided with an equipotential grounding grid using copper bars 25 mm x 3 mm or BV-25 sqmm conductors, with a grid size of 600 mm x 600 mm; all metal conduits, cable trays, and cabinets shall have reliable grounding connections.

4. System commissioning and integrated commissioning acceptance

Low-voltage system commissioning follows the principles of single equipment before system, local before remote, and subnet before backbone. Commissioning process: single equipment commissioning with point-by-point I/O testing, sensor accuracy calibration, and actuator stroke testing; subsystem commissioning with DDC controller PID parameter tuning and logic verification; network commissioning with IP address allocation, VLAN division, route configuration, and BACnet device discovery; linkage commissioning with fire linkage, security linkage, and BA linkage.

Still have a specific question? Ask a MEP expert

12 hotel MEP experts online, answers cite standard clauses you can verify.

Ask free →

Engineering reference only — verify against project conditions and the latest codes.